| Labor Import |
Modify Labor Master import from DOS version to accommodate divisional segregation |
| Change Order Costing |
Corrected for wrong message coming up ‘XX openings need to be priced in the original’ where the openings were the ones having frame elevations assigned |
| Elevations Quantities |
Corrected for situation where a different elevation is drawn for opposite hands was causing a problem with doubling the quantity |
| Costing window |
When project cleared, hide Change Order button. If clicked while the project is disabled, it gives a wrong message that the project has been deleted |
| Change order selection window |
Sold date was not showing if change order was sold and extra sections, other that the ones included in the project costing, were present in the project setup window |
| Default Preps Window for Elevations |
Manufacturers that are ‘D/F Parts’ were not showing in the list of available parts. |
| Pair Communicating Quantities |
Double default quantity for deadlocks, locksets and exit devices ( DL, LO, and EX) for PC (Pair Communicating) and AA (Pair Both Active) openings and assign one to each leaf. |
| Reuse Opening Numbers |
When openings get deleted by having them renamed in the complete window, the old opening number could not be re-entered |
| Keying Window |
Added Reorder options in the right click menu for the list – also, eliminated sort sequence column (it remains maintained in the background by the system). |
| Advantage discounts window |
Doors & frame discounts tab has been removed |
| Catalog Maintenance |
Mfg Attributes Menu option: Attribute Description Sequence Tab – automatically fill in mfg, type and increment sequence from the line above |
| Generic Hollow Metal Catalog |
Corrected for error HG copying as WE |
| Complete Opening Window |
When opening is locked in the original (meaning that the opening has been changed via a change order already) then, allow direct change in the opening area for the following columns: interior/exterior, location a, to/from, location b, fire rating, degree of opening, building area, opening description; door area for architect type, elevation, sill, notes; frame area for architect type, elev # - only where costing method of old and new are automatic, wall conditions, notes hardware area for selected images |
| Catalog Maintenance |
Renamed Prep Discounts into Prep Net Pricing |
| Heading Builder |
Save heading building criteria per project. Also, when manually assigning a heading, the system looks to this project specific criteria to determine if the opening can be added to the desired heading |
| Copy Hardware |
When heading assigned manually and hardware list is copied from an existing opening within the heading, the product handing is now recalculated. |
| Complete Window |
Change Orders - Do not allow changes to openings with ‘Cancelled’ status |
| Heading Builder |
Added opening description as a part of heading builder criteria |
| Tax Rate |
Allow tax rate to be 4 decimal places. |
| Heading Builder |
Corrected heading builder for situation where opening sizes are in 3'0"7'0" format. |
| Suppliers for Reports |
Modify Supplier Selection from reports to recognize both home division and all authorized divisions. |
| Project Setup |
Delivery Schedule Tab: 1. Change tab name from 'Delivery Schedule' to 'Scheduling' 2. Use # sign when searching for a Null value and use ‘1/1/1900’ to search for Null date values. 3. Added a column for 'Section' 4. Added sort feature for column headings. |
| Product Notes |
Corrected for product specific notepad notes not being brought over into the headings when headings were built automatically. |
| Door / Frame Lump Sum |
Correction for doors/frames allocate lump sum – lost when project was copied into detailing and hands were defined |
| Leaf Size Split |
Corrected for leaf size split for PC (Pair Communication) openings in takeoff window and default frame description to SGL. |